The purpose of this project is to take the first step in creating redundancy in terms of regulator power between Vault 12 and the West Vault. Vault 12 and the West Vault are the main airfield lighting vaults that support CVG’s runways and taxiways. These two vaults are critical pieces of CVG infrastructure in order to maintain airfield operations. The scope for this project involves the upgrade of electrical components, such as switchgears and transformers, in Vault 12 to allow for the appropriate sizing as CVG works towards achieving this redundancy. NOTE: This project does not include any work in the West Vault.
Submission Deadline: 19-Sep-2019 at 2:00 p.m. ET
Submitting Organization: Kenton County Airport Board-Cincinnati/Northern Kentucky International Airport (CVG)
19 81 Vault 12 Switchgear Replacement Upgrades